A bill of at least $17 million has landed back in the lap of Te Whatu Ora Health New Zealand (HNZ) after a saving on Dunedin鈥檚 new hospital complex was approved by mistake.
This comes as HNZ has yet to confirm whether it will recommend or decline proposals to severely cut back the size and scope of the new Dunedin Hospital.
A HNZ report written in September details the University of Otago proposal to take over HNZ鈥檚 share of the cost of the Interprofessional Learning Centre to allow savings to be made.
The centre is planned as a collaboration between HNZ, the university and Te Pukenga, formerly Otago Polytechnic.
It has not been finalised and the university withdrew its funding offer in February.
However, this update was not incorporated into written advice to ministers.
鈥淎ccordingly, the record shows ministers approving a saving that did not, and does not, exist,鈥 the report said.
The centre will be constructed just north of the hospital鈥檚 outpatient building, in Cumberland St.
Cost division was settled two years ago, when each party agreed to pay in proportion to the space they would occupy, the report said.
鈥淭he [Ministry of Health] had earlier set aside $17 million, being the estimated cost of the [professional development unit].鈥
With the new hospital facing cost pressures, the university proposed to take over the construction of the centre, expand its own share of the build, and cover the hospital鈥檚 share.
鈥淭here was an urgent effort under way to identify some quick savings.
鈥淚t was quickly incorporated in a paper to ministers being drafted up at the time.鈥
When the offer was withdrawn, due to the university鈥檚 spare capital evaporating, the Ministry of Health was notified and responded, emails within the report show.
The error damaged the 鈥渢rust and goodwill鈥 on which the collaborative project was conceived.
鈥淗ad the [university] never made the offer to help late last year, we would not be in this position,鈥 the report said.
罢丑别听Otago Daily Times聽reported in 2021 the approximate cost for the build 鈥 according to a Cabinet paper 鈥 was $51 million.
The projected cost of the centre has risen to $115.5 million, due to inflation and a planned size increase by the university.
University chief operating officer Stephen Willis said several funding and delivery options had been discussed, but none had been formally endorsed.
The centre was a 鈥渦nique opportunity鈥 for the project partners to collaborate for the mutual benefit of students, staff and the community.
鈥淎s such, the university remains committed to the joint vision of the [centre] and continues to discuss options and potential ways forward with its project partners.鈥
The facility is planned to be operational by 2027. - ODT
Take your Radio, Podcasts and Music with you
Get the iHeart App
Get more of the radio, music and podcasts you love with the FREE iHeartRadio app. Scan the QR code to download now.
Download from the app stores
Stream unlimited music, thousands of radio stations and podcasts all in one app. iHeartRadio is easy to use and all FREE